Gedabek Gold Mine/ Azerbaijan
Loader
yeo group

Gedabek Gold Mine / Azerbaijan

Project Description: Gedabek Gold Mine Protection & Automation Project ;

For the year ended 31 December 2016, total gold production as doré bars and as a constituent of the copper and precious metal concentrate totaled 65,394 ounces, which was a decrease of 6,638 ounces in comparison to the production of 72,032 ounces for the year ended 31 December 2015. 

End-user: Confidential;

Scope of works:

  • All Engineering and Supervision;
  • Installation of SCADA and Automation System;
  • ABB Freelance DCS System;
  • Redundant SCADA System, 2000 hardwired I/Os, 500 soft I/Os;
  • Communication of 10 pcs. MV relays and 10 pcs. Energy Analyzers;
  • Tests: Cold and Hot Testing, Functional Testing, Start-up Testing;
  • Commissioning, Training and Documentation;
Bikilitaş Cement Plant / Turkey

Turnkey Electrification & Automation

Iron & Steel Factory / Turkey

Desalination Plant Electrification & Automation

Gedabek Gold Mine / Azerbaijan

Gold Mine Protection & Automation Project

Medcem Cement Factory / Turkey

Factory Substation Protection & Automation Project

yeo group